__BN_SlabCutoutVoid

Reference Image

__BN_SlabCutoutVoid

📐 Drawing Conventions

  • Slab Cut Voids should be within the BUA outline for habitable floors and within the parking polyline for parking floors.
  • Slab Cut Voids drawn within a floor plan are considered to be at the floor level, not the ceiling level, for all floors except the lowest basement.
  • For the lowest basement, voids are considered at the ceiling level and are not deducted from the gross parking area.
  • All Slab Cut Voids in the basement floor plan should be aligned with those in the floor plan immediately above ground level. Example: If there is a stilt floor above the basement floors, a Slab Cut Void polyline should be aligned with the Slab Cut Void polylines in the basement floor plan.
  • Slab Cut Void area will be considered in the calculation of the total basement ventilation area.

📏 Allowed Geometric Types

  • Closed Polyline

🏗️ Applicable Project Types

  • Building Permission
  • Layout With Housing And Gated Community & Layout With Housing Without Gated Community